Capital Projects Update - Cruise Terminal 8
PortCanaveral
👁️ 185 views📅 4 years ago⏱️ 1:02
YouTube Video Description↓
We are making improvements to the moorings. This project kicked off in May and since then all steel pipe piles have been installed. Currently the form work is being completed for the mooring dolphin platform and the catwalk piles are being poured. Simultaneously the project’s electrical and IT work is underway as well. The date of completion is just around the corner as we aim for April of this year.